undergraduate thesis
Protecting small construction pit in incoherent soil below water boundry

Matea Majer (2016)
University North
University centre Varaždin
Department of Civil Engineering
Metadata
TitlePrimjer zaštite manje građevinske jame u nekoherentnom tlu ispod razine podzemne vode
AuthorMatea Majer
Mentor(s)Božo Soldo (thesis advisor)
Abstract
Tema samog rada je zaštita manje građevinske jame u nekoherentnom tlu ispod razinepodzemne vode, stoga se i čitav rad bazira na toj tematici. Kompletni rad je podijeljen na četiri glavna poglavlja, gdje se u prvom poglavlju govori općenito o terminu nekoherentnog tla kao i pojmu građevinskih jama zajedno s njihovim problemom vezanim uz djelovanje podzemne i oborinske vode. Drugo poglavlje bavi se metodama zaštite građevinskih jama od metoda s dijafragmama od pilota pa do zaštite građevinske jame čeličnim žmurjem. U trećem poglavlju data je problematika građevinske jame Hotela Park u Varaždinu, te je provedeno kompletno dimenzioniranje zaštite građevinske jame određivanjem tipa zaštite zidova jame, te rješavanje problema podzemnih voda.U četvrtom poglavlju dat je osvrt na rezultate dobivene dimenzioniranjem građevinske jame.
Parallel title (English)Protecting small construction pit in incoherent soil below water boundry
Committee MembersMatija Orešković (committee chairperson)
Aleksej Aniskin (committee member)
Željko Kos (committee member)
GranterUniversity North
Lower level organizational unitsUniversity centre Varaždin
Department of Civil Engineering
PlaceKoprivnica
StateCroatia
Scientific field, discipline, subdisciplineTECHNICAL SCIENCES
Civil Engineering
Construction Organization and Technology
Study programme typeprofessional
Study levelundergraduate
Study programmeCivil Engineering
Academic title abbreviationbacc. ing. aedif.
Genreundergraduate thesis
Language Croatian
Defense date2016
Parallel abstract (English)
The theme of the work is to protect the small construction pit in incoherent soil below thewater table, so the whole work is based on that theme.The complete work is divided into four major sections, where the first chapter speaksgenerally about the term incoherent soil as well as the concept of construction pits togetherwith their problems related to the effect of groundwater and rainwater.The second chapter deals with methods to protect construction pit method with thediaphragms of the pilots to the protection of the construction pit steel sheet piling.In the third chapter, given the problems of the construction pit Park Hotel in Varazdin, andwas conducted completely sizing protect construction pit by specifying the type of protectionof the walls of the cave, and problem solving groundwater.In the fourth chapter provides an overview of the results from the dimensioning of theconstruction pit.
Parallel keywords (Croatian)zaštita
Resource typetext
Access conditionOpen access
Terms of usehttp://rightsstatements.org/vocab/InC/1.0/
URN:NBNhttps://urn.nsk.hr/urn:nbn:hr:122:983953
CommitterJasna Kosić